Little Beach, Nelson Bay

ProjectExpected start monthExpected completion monthStatusBudget
Boat ramp and pathwaysJuly 2021November 2021Complete$1.7m
Amenities replacementJuly 2022September 2022Scheduled$180k
Retaining wall replacementTBCTBCScheduled$50k
Playground updateTBCTBCScheduled$75k

Latest updates

11 March 2022

Planning is underway on the new amenities block and beach access path at Little Beach. This project is scheduled for commencement early in the new financial year.

Project description

  • Replace boat ramp and upgrade pathways. This project has received funding from the NSW Government's Boating Now funding program.
  • Amenities are currently in a redesign phase following community feedback in March 2021. This project is expected to be ready for construction in 2022.
  • Replacement of the retaining wall at Little Beach Reserve.
  • Update of the playground at Little Beach Reserve.