Little Beach, Nelson Bay
Project | Expected start month | Expected completion month | Status | Budget |
---|---|---|---|---|
Boat ramp and pathways | July 2021 | November 2021 | Complete | $1.7m |
Amenities replacement | July 2022 | September 2022 | Scheduled | $180k |
Retaining wall replacement | TBC | TBC | Scheduled | $50k |
Playground update | TBC | TBC | Scheduled | $75k |
Latest updates
11 March 2022
Planning is underway on the new amenities block and beach access path at Little Beach. This project is scheduled for commencement early in the new financial year.
- download the September 2021 newsletter (1.9 MB)
- view the Little Beach boat ramp site signage (249 KB)
- view the latest media release
- download the June 2021 newsletter (550 KB)
- download the March 2021 newsletter (770 KB)
Project description
- Replace boat ramp and upgrade pathways. This project has received funding from the NSW Government's Boating Now funding program.
- Amenities are currently in a redesign phase following community feedback in March 2021. This project is expected to be ready for construction in 2022.
- Replacement of the retaining wall at Little Beach Reserve.
- Update of the playground at Little Beach Reserve.