SegmentExpected start monthExpected finish monthStatusBudget
SeahamJanuary 2021March 2022In progress$1.8m
Seaham Seg 130October 2021April 2022In progress$580k
Glen Oak Seg 270November 2021April 2022In progress$531k

Latest updates

25 February 2022

Glen Oak Seg 270: The second coat of seal has now been completed. Line marking is scheduled to complete this project but is delayed by wet weather.

Project Details

These road works are funded by the Australian Government.

Priority upgrades along Clarence Town Road between Raymond Terrace and Dungog. Upgrade works will include reconstruction, widening and resealing along the route.

The Project will improve freight efficiency and road safety, improve connectivity between people and jobs and facilitate movement of goods to markets.

Glen Oak

Pavement rehabilitation, Oakendale Rd north to Hunter Water crossover

Seaham

Pavement rehabilitation, curves south of Croft Road.
Further works will include road pavement improvements including bitumen seal, site clean up and tree planting. Final seal and line marking to be completed in December.