Clarence Town Road upgrades
Segment | Expected start month | Expected finish month | Status | Budget |
---|---|---|---|---|
Seaham | January 2021 | March 2022 | In progress | $1.8m |
Seaham Seg 130 | October 2021 | April 2022 | In progress | $580k |
Glen Oak Seg 270 | November 2021 | April 2022 | In progress | $531k |
Latest updates
25 February 2022
Glen Oak Seg 270: The second coat of seal has now been completed. Line marking is scheduled to complete this project but is delayed by wet weather.
Project Details
These road works are funded by the Australian Government.
Priority upgrades along Clarence Town Road between Raymond Terrace and Dungog. Upgrade works will include reconstruction, widening and resealing along the route.
The Project will improve freight efficiency and road safety, improve connectivity between people and jobs and facilitate movement of goods to markets.
Glen Oak
Pavement rehabilitation, Oakendale Rd north to Hunter Water crossover
- Read the latest resident notification
Seaham
Pavement rehabilitation, curves south of Croft Road.
Further works will include road pavement improvements including bitumen seal, site clean up and tree planting. Final seal and line marking to be completed in December.
- Read the latest Clarencetown Road newsletter