Oakendale Rd Glen Oak – Notts Creek Bridge Renewal

Expected start monthExpected completion monthStatusBudgetContribution
September 2023December 2023In progress$557,000External funding 100 

Latest update

24 November 2023

The culvert base slab had been formed, reinforcement completed and concrete poured. The placement of the culverts will be completed this week.


Project description

Council are pleased to advised that funding is available from the Federal Bridges Renewal Program and NSW State Government Fixing Country Bridges Grant, to allow us to undertake a much needed upgrade of Notts Creek Bridge.

The works include:

  • Construction of temporary side access track
  • Demolish the existing bridge
  • Construct new box culvert bridge (single lane) and associated minor road works
  • Remove the temporary access track once the new bridge is operating

The side access track will have pipes installed in the creek bed with gravel placed over the top providing alternate access. Emergency services, waste services and postal deliveries will remain as normal utilizing the side access track. The access track will be low level in nature.

The project is scheduled to take approximately 10 weeks weather permitting.