Newline Road, East Seaham

Expected start monthExpected completion monthStatusBudgetContribution
March 2022October 2022Completed$1.4mPSC funding 10 

Seg 290 - 300. Pavement rehabilitation

Latest update

28 November 2022

Over the past fortnight we have completed the final 7mm construction seal before adding new linemarking and pavement markers. While the project appears completed we still have some farm fencing to reinstate and a power pole adjustment to complete.