Tanilba Road, Mallabula

Expected start monthExpected completion monthStatusBudgetContribution
June 2022March 2023In progress$1.4mPSC funding 100 

Widening, kerb and gutter construction from Bay Street to Mallabula Road.

Latest updates

30 January 2023

Stormwater installation has continued in this short week with Ausgrid undertaking power pole holding to allow deep trenching past power poles.