Tanilba Road, Mallabula

Expected start monthExpected completion monthStatusBudgetContribution
June 2022November 2022Scheduled$1.9mPSC funding 100 

Widening, kerb and gutter construction from Bay Street to Mallabula Road.

Latest updates

26 September 2022

Progress continued on pavement over the past week. With no surprise considering the current ground conditions through our LGA, unsuitable subgrade sections were removed and replaced.