Swan Bay Road

ProjectExpected start monthExpected completion monthStatusBudgetContribution
Road widening - Stage 3 (Seg 50-60)August 2022October 2022Nearing completion$500kPSC funding 100 
Road rehabilitation - Seg 160July 2022March 2023Scheduled$451kPSC funding 100 

Latest updates

1 March 2023

Segment 50-60: Final construction seal scheduled for late March 2023 (weather permitting). Line marking will follow shortly after in early April to complete this project.

Segment 160: Fencing relocation on the new road alignment was completed in December 2022. Relocation of Telstra’s assets is scheduled to commence early March (weather permitting).

Project description

Progressive sealed road widening from Stage 2 towards Ponds Road (Seg 50-60) and road rehabilitation (Seg 160).