Six Mile Road, Eagleton

Expected start monthExpected completion monthStatusBudgetContribution
August 2022December 2022Completed$1.01mPSC funding 30 

Latest updates

23 January 2023

The major upgrade works (initial seal and drainage) were completed in time for Christmas. Guardrail installation was postponed due to contractor delays, which is now scheduled for the end of January. Asphalt works at the intersection with the Pacific Highway will also be undertaken in early February.

Project Description

Road rehabilitation.