Seaham Road, Nelsons Plains

Expected start monthExpected completion monthStatusBudgetContribution
January 2023February 2023In progress$1,059,574.00External funding 100 

Latest updates

23 January 2023

Project commenced last week on the intersection upgrade at Seaham Rd and Hinton Rd. Initial drainage works are progressing.

Project description

Intersection upgrade with Hinton Road, Nelsons Plains

Council is undertaking intersection upgrade and road reconstruction works on Seaham Road and Hinton Road intersection which is scheduled to begin early January 2023.

This project has been made possible by Special Purpose Grant Funding Agreement between the Australian Government, Dungog Shire Council, Port Stephens Council and Transport for NSW.

The aim of this project is to improve the condition and safety of the road and intersection.

The works will include:

  • Road Reconstruction (project map shown below)
  • Intersection upgrades
  • Water main replacement
  • Minor drainage works

There will be some temporary traffic changes to ensure the work site is safe for workers and motorists. Please follow our traffic controller’s directions. Our construction team will notify residents of impacts to driveway access throughout the project.

These works are scheduled to be completed within 6 weeks (weather dependant).

Site plan - Seaham and Hinton Rd intersection works