Raymond Terrace depot
Expected start month | Expected completion month | Status | Budget | Contribution |
---|---|---|---|---|
April 2022 | May 2023 | In progress | $2.97m | ![]() |
Demolition of existing depot building and construction of new Council depot.
Latest updates
29 May 2023
The Administration Building is all but complete now with only commissioning and defect rectification left to be done. The storage area and workshop are due to be complete in early June. Upgrade of the high voltage electrical connection will be done soon after, prior to Council inhabiting the new development. With the exception of defects and car parking areas, all concrete pavement areas are now complete. Landscaping is underway.