Newline Road, East Seaham
Expected start month | Expected completion month | Status | Budget | Contribution |
---|---|---|---|---|
March 2022 | October 2022 | Completed | $1.4m | ![]() |
Seg 290 - 300. Pavement rehabilitation
Latest update
28 November 2022
Over the past fortnight we have completed the final 7mm construction seal before adding new linemarking and pavement markers. While the project appears completed we still have some farm fencing to reinstate and a power pole adjustment to complete.