Newline Road, East Seaham

Expected start monthExpected completion monthStatusBudgetContribution
March 2022September 2022In progress$1.4milPSC funding 10 

Seg 290 - 300. Pavement rehabilitation

Latest update

26 September 2022

The team has now completed the final section of poor subgrade replacement. Next week we import the new stabilized base material before putting concrete barriers in place to enforce a ‘hard’ road closure to allow the stabilment to set without impacts from traffic ahead of the primer seal scheduled for the first week of October and reopening of the road.

See latest notification of works.