King Park, Raymond Terrace
Project | Expected start month | Expected completion month | Status | Budget | Contribution |
---|---|---|---|---|---|
Building refurbishment | October 2022 | February 2023 | In progress | $445k | ![]() |
Pathway construction | October 2022 | February 2023 | In progress | $547k | ![]() |
Replace vehicle barriers and fencing | April 2023 | June 2023 | Scheduled | $100k | ![]() |
Building refurbishment and pathway construction and replace vehicle barriers and fencing.
Latest updates
23 January 2023
Works have commenced on the upgrades to sports buildings and the shared path installation at King Park, Raymond Terrace. The shared path construction has started at Newline Road and will terminate near the boat ramp at the bridge. Building works underway include new change room partitions, new carpet, painting and installation of AV equipment. Works are expected to be finalised around the end of February.