Henderson Park, Lemon Tree Passage
Project | Expected start month | Expected completion month | Status | Budget | Contribution |
---|---|---|---|---|---|
Shade sail installation | May 2022 | June 2022 | Completed | $91k | ![]() |
Irrigation Upgrade | March 2023 | April 2023 | Scheduled | $10k | ![]() |
Shade sail installation and irrigation upgrade.
Latest updates
15 May 2023
Shade sail over the foreshore deck at Henderson Park, Lemon Tree Passage is complete. The footings and columns were installed in June and four weeks was allowed for the concrete footings to cure. The shade sail was installed and tensioned this week to complete the work.
Irrigation works at Henderson Park are now complete and operational.