Ferodale Road
Project | Expected start month | Expected completion month | Status | Budget | Contribution |
---|---|---|---|---|---|
Pavement rehabilitation Seg 100 - Medowie Road - roundabout to Peppertree Road. | March 2023 | March 2023 | Scheduled | $189k | ![]() |
Blackspot program | December 2022 | February 2023 | In progress | $423k |
Latest updates
23 January 2023
Blackspot program: The new kerb and guttering and kerb extensions were poured this week. The team onsite are now focusing on preparing new footpath connections to pour early next week and have safe access ready for the kids to return to school.