Brandon Park, Seaham

Expected start monthExpected completion monthStatusBudgetContribution
August 2022May 2023In progress$783kPSC funding 20

Latest updates

29 May 2023

Amenities: With the building structure now complete and roof sheeting on, finishes trades have commenced. While photos were taken earlier in the week, waterproofing and electrical rough-in has since been completed ready for ceiling to be installed and tiling to commence.

Court surface: Brandon Park Netball Court Surface painting is now complete and available for community play. Multi-Sport Court will be completed next week - weather permitting.

Project overview

Amenities building and sport court upgrades include:

  • accessible amenities addition
  • tiered seating
  • reinforced concrete carpark
  • building refurbishment
  • Removal of existing tennis court to install new multi sport court