Boomerang Park basketball court
Expected start month | Expected completion month | Status | Budget | Contribution | |
---|---|---|---|---|---|
Basketball Court | December 2022 | January 2023 | Completed | $15k | TBC |
BBQ replacement | TBC | TBC | TBC | TBC | TBC |
Latest updates
20 February 2023
Line marking was applied to the new basketball court at Boomerang Park, Raymond Terrace. The court is on the disused croquet court opposite the men’s shed in Boomerang Park and is apparently getting plenty of use already. Park bench seating will be installed next week.
Project description
Boomerang Park Basketball Court (conversion of croquet court) and BBQ replacement.