Aliceton Reserve Project Update banner image

Aliceton Reserve, Karuah

Project description

Relocation of playground and amenities from Memorial Park to Aliceton Reserve.

Project Expected start month Expected completion monthStatusBudgetContribution
Amenities TBC TBC Scheduled $180k TBC
Playground May 2023 June 2023 Scheduled $150k TBC

Latest updates

20 March 2023

Following a community survey coordinated through the Community Engagement team, the preferred option has been selected for the new playground to be installed at Aliceton Reserve. It was great to see a range of feedback received through the survey process, leveraging off the previous Karuah Place Plan process. A mock-up of the preferred option (Option A) is shown below, and production of the equipment is now underway by our Contractor Moduplay with work expected to commence on site in May 2023.