Council Administration Building carpark

Expected start monthExpected completion monthStatusBudget
September 2021February 2022In progress$500k

Temporary carpark extension.

Latest updates

18 March 2022

Works on the lighting poles has been initiated with trenching started for the electrical and communications wiring.  Works are expected to be completed by the end of next week, weather permitting.