Lemon Tree Passage Rd, Salt Ash

StageExpected start monthExpected completion monthStatusBudget
Stage 1May 2020August 2020Complete$1.069m
Stage 2May 2021December 2021In progress$360k

Latest updates

23 August 2021

Since the completion of asphalt on the intersection of Michael Drive last Friday, line marking has been completed this week. A barrier rail over the top of the headwall has also been installed. A second coat of spray seal will be applied in December 2021.

Project description

Stage 1:

This project is Black Spot funded by the NSW Government. It involves road pavement rehabilitation, road widening and safety improvements between 192 Lemon Tree  Passage Road and Rookes Road.

Stage 2:

This project is primarily Blackspot funded by the Australian Government. Project is in the area of Michael Drive and will include wide painted centre median, improved sealed shoulder on curve, guardrail, signage and improved street lighting at intersection.